logo

Overhauls at Grupa Lotos S.A.’s Gdańsk Refinery in 2007
Report no. 96/20052006-12-28

The Management Board of the Grupa LOTOS S.A. reports that in accordance with the adopted plan no repair shutdown is to take place at Grupa LOTOS S.A.’s Gdańsk Refinery in 2007. A stoppage of the hydrocracker has been scheduled for spring 2007 in connection with the need to replace used catalyst. During the stoppage, which is expected to last about two weeks, brief shutdowns of other production installations are possible, to enable the execution of repair and maintenance work. Oil refining is not planned to be interrupted at any time during the hydrocracker stoppage or throughout the remaining part of 2007. The stoppage related to the need to replace the hydrocracker catalyst will have no negative impact on the scale or regularity of supplies of petroleum products by the LOTOS Group. Legal basis for the report: Art. 56.1.1 of the Act on Offering – Inside Information